Report_Id:   122334   Est NO  0007

Date:03/28/2013

COMMONWEALTH OF KENTUCKY

TRANSPORTATION CABINET


Contract ID 122334 Estimate Number 0007 Estimate Type PROGRESS
District Office PADUCAH (01300)  Leonard, Jordan A.

Contractor CHESTER BROSS CONSTRUCTION CO W/O/S BROSS HOLDING GROUP INC ADDR SN 0 VC Code VC0000170584
6739 COUNTY ROAD 423
PALMYRA , MO , 63461
Pay Period 02/08/2013  TO  02/22/2013
Date Approved 03/07/2013
Primary Proj Number MP07300451201
Project No. FE01 073 0045 007-009, FE01 073 0062 011-012
Primary County MCCRACKEN
Name of Road US 45 AND US 62 IN MCCRACKEN COUNTY
Description US 45 AND US 62 IN MCCRACKEN COUNTY
     
     
Date Let 09/14/2012 Formal Acceptance
Date Awarded 09/26/2012 Date Work Began 10/26/2012
Date Contract Executed 10/16/2012 Open To Traffic
Date NTP Issued 06/16/2012 Actual Completion Date

Current Contract Amount

$1,080,726.00

Total to Date

Prev to Date

This Estimate

Original Amount

$1,080,726.00

Total Earnings

$655,929.90

$601,102.13

$54,827.77

Percent Complete

60.69

Stockpiled Materials

$0.00

$0.00

$0.00

Funds Available

$424,796.10

Gross Earnings

$655,929.90

$601,102.13

$54,827.77

Total Change Orders

$0.00

Other Adjustments

$0.00

$0.00

$0.00

TOTAL

$655,929.90

$601,102.13

$54,827.77

Contract Id 122334

Change Order Summary

County MCCRACKEN
Estimate Nbr 0007 Project Number FE01 073 0045 007-009, FE01 073 0062 011-012
Contractor CHESTER BROSS CONSTRUCTION CO W/O/S BROSS HOLDING GROUP INC Period 02/08/2013  TO  02/22/2013
 
 
CHANGE ORDERS HISTORY  
CHANGE ORDER NBR DESCRIPTION STATUS APPROVAL DATE TOTAL CO AMOUNT CONTRACT TIME ADJUSTED
 
 
 
 

CONTRACT ADJUSTMENTS HISTORY

Contract Adjustments

 

 

Adjustment Description

Est No

Adjustment Amount

Line Item Adjustments History
PROJECT ITEM NBR DESCRPITION TYPE EST NO

ADJ QUANTITY

UNIT PRICE

ADJUSTED AMOUNT

Contract Id 122334

COMMONWEALTH OF KENTUCKY

County MCCRACKEN
Contract Type JPCR   JPC PAVEMENT REPAIRS

TRANSPORTATION CABINET

Primary Project Number MP07300451201
Estimate Nbr 0007 Period 02/08/2013  TO  02/22/2013
Contractor CHESTER BROSS CONSTRUCTION CO W/O/S BROSS HOLDING GROUP INC
 
Project MP07300451201 Fed/State Project Number FE01 073 0045 007-009 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0010 DGA BASE 00001 TON 811.00 811.000 202.780 202.780 18.50 3,751.43
0020 BARRICADE-TYPE III 02014 EACH 3.00 3.000 2.000 2.000 140.00 280.00
0030 JPC PAVEMENT-10 IN/24 02024 SQYD 7,050.00 7,050.000 356.667 6,304.262 6,660.929 73.00 26,036.69 486,247.81
0040 REMOVE PCC PAVEMENT 02058 SQYD 7,050.00 7,050.000 356.667 6,304.262 6,660.929 11.00 3,923.33 73,270.21
0050 PCC PAVEMENT DIAMOND GRINDING 02060 SQYD 16,510.00 16,510.000 6,724.000 4,304.000 11,028.000 3.30 22,189.20 36,392.40
0060 SAW-CLEAN-RESEAL TVERSE JOINT 02115 LF 5,000.00 5,000.000 0.000 0.000 1.10 0.00
0070 SAW-CLEAN-RESEAL LONGIT JOINT 02116 LF 7,000.00 7,000.000 0.000 0.000 1.10 0.00
0080 ROADWAY EXCAVATION 02200 CUYD 1,175.00 1,175.000 59.444 1,057.356 1,116.800 30.00 1,783.32 33,504.00
0090 SIGNS 02562 SQFT 250.00 250.000 80.000 80.000 9.50 760.00
0100 MAINTAIN & CONTROL TRAFFIC US 45 US 45 02650 LS 1.00 1.000 0.500 0.500 8,875.00 4,437.50
0110 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 4.00 4.000 4.000 4.000 1,130.00 4,520.00
0120 ARROW PANEL 02775 EACH 2.00 2.000 2.000 2.000 735.00 1,470.00
0130 CONDUIT-1 1/4 IN 04793 LF 10.00 10.000 0.000 0.000 10.50 0.00
0140 TRENCHING AND BACKFILLING 04820 LF 10.00 10.000 0.000 0.000 5.25 0.00
0150 PREFORMED LOOP/LEAD-IN 04894 LF 175.00 175.000 165.000 165.000 18.90 3,118.50
0160 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 11,000.00 11,000.000 2,633.000 0.000 2,633.000 0.34 895.22 895.22
0170 PAVE MARKING-THERMO STOP BAR-24IN 06568 LF 302.00 302.000 0.000 0.000 12.60 0.00
0180 PAVE MARKING-THERMO STR ARROW 06573 EACH 4.00 4.000 0.000 0.000 136.50 0.00
0190 PAVE MARKING-THERMO CURV ARROW 06574 EACH 14.00 14.000 0.000 0.000 136.50 0.00
0200 PAVE MARKING-THERMO COMB ARROW 06575 EACH 2.00 2.000 0.000 0.000 315.00 0.00
0210 FUEL ADJUSTMENT 10020NS DOLL 1,053.00 1,053.000 0.000 0.000 1.00 0.00
0220 PREFORMED QUADRAPOLE LOOPS 20453ES835 LF 510.00 510.000 408.000 408.000 17.85 7,282.80
0230 SAW-CLEAN-RESEAL RANDOM CRACKS 21173EC LF 100.00 100.000 0.000 0.000 5.46 0.00
Project MP07300451201 Fed/State Project Number FE01 073 0045 007-009 Category 0002 DEMOBILIZATION
0240 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 11,250.00 0.00

SUBTOT

$54,827.76

$655,929.88

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00

 

 

 

Project MP07300621201 Fed/State Project Number FE01 073 0062 011-012 Category 0001 ROADWAY
LINE ITEM NUMBER ITEM DESCRIPTION ITEM NO. UNIT PLAN QTY CURRENT QUANTITY QUANTITY PAID THIS EST QUANTITY PAID PREV. EST QUANTITY PAID TO DATE UNIT PRICE AMOUNT PAID THIS EST AMOUNT PAID TO DATE
0010 DGA BASE 00001 TON 316.00 316.000 0.000 0.000 18.50 0.00
0020 BARRICADE-TYPE III 02014 EACH 3.00 3.000 0.000 0.000 140.00 0.00
0030 JPC PAVEMENT-10 IN/24 02024 SQYD 2,742.00 2,742.000 0.000 0.000 73.00 0.00
0040 REMOVE PCC PAVEMENT 02058 SQYD 2,742.00 2,742.000 0.000 0.000 11.00 0.00
0050 PCC PAVEMENT DIAMOND GRINDING 02060 SQYD 4,136.00 4,136.000 0.000 0.000 3.30 0.00
0060 SAW-CLEAN-RESEAL TVERSE JOINT 02115 LF 2,000.00 2,000.000 0.000 0.000 1.10 0.00
0070 SAW-CLEAN-RESEAL LONGIT JOINT 02116 LF 3,000.00 3,000.000 0.000 0.000 1.10 0.00
0080 ROADWAY EXCAVATION 02200 CUYD 459.00 459.000 0.000 0.000 30.00 0.00
0090 SIGNS 02562 SQFT 250.00 250.000 0.000 0.000 9.50 0.00
0100 MAINTAIN & CONTROL TRAFFIC US 62 US 62 02650 LS 1.00 1.000 0.000 0.000 8,875.00 0.00
0110 PORTABLE CHANGEABLE MESSAGE SIGN 02671 EACH 2.00 2.000 0.000 0.000 1,130.00 0.00
0120 ARROW PANEL 02775 EACH 2.00 2.000 0.000 0.000 735.00 0.00
0130 CONDUIT-1 1/4 IN 04793 LF 20.00 20.000 0.000 0.000 10.50 0.00
0140 TRENCHING AND BACKFILLING 04820 LF 20.00 20.000 0.000 0.000 5.25 0.00
0150 PREFORMED LOOP/LEAD-IN 04894 LF 200.00 200.000 0.000 0.000 18.90 0.00
0160 PAVE STRIPING-PERM PAINT-4 IN 06514 LF 5,000.00 5,000.000 0.000 0.000 0.34 0.00
0170 PAVE MARKING-THERMO STOP BAR-24IN 06568 LF 123.00 123.000 0.000 0.000 12.60 0.00
0180 PAVE MARKING-THERMO STR ARROW 06573 EACH 6.00 6.000 0.000 0.000 136.50 0.00
0190 PAVE MARKING-THERMO CURV ARROW 06574 EACH 8.00 8.000 0.000 0.000 136.50 0.00
0200 FUEL ADJUSTMENT 10020NS DOLL 411.00 411.000 0.000 0.000 1.00 0.00
0210 PREFORMED QUADRAPOLE LOOPS 20453ES835 LF 612.00 612.000 0.000 0.000 17.85 0.00
0220 SAW-CLEAN-RESEAL RANDOM CRACKS 21173EC LF 100.00 100.000 0.000 0.000 5.46 0.00
Project MP07300621201 Fed/State Project Number FE01 073 0062 011-012 Category 0002 DEMOBILIZATION
0230 DEMOBILIZATION 02569 LS 1.00 1.000 0.000 0.000 11,250.00 0.00

SUBTOT

$0.00

$655,929.88

LNNBR STOCKPILE ADJUSTMENTS

UNIT

ADJ. QUANTITY

EST NBR

UNIT PRICE

ADJUSTED AMOUNT

SUBTOT

$0.00