2009-06-
Statewide Airport Pavement Management QUESTION
1: Is this an update of
an existing MicroPAVER APMS or will this be an initial inspection and implementation? ANSWER
1: It will be an
initial inspection and implementation. QUESTION
2: What type of analysis do
you want performed (just pavement condition data gathered, entered into MicroPAVER, and a list of Pavement Condition Index (PCI)
values compiled and pavement condition maps prepared or a full pavement
management analysis including a multi-year maintenance and rehabilitation
program)? ANSWER
2: It will most likely
be in-between the two scenarios mentioned. The exact scope will be
determined after selection, based on available funding. Consultants
should plan on, at the least, gathering data, entering it into MicroPAVER, compiling a list of PCI's, and some form of
pavement analysis, including recommendations on preferred pavement
maintenance required. QUESTION
3. What type of reports do
you want generated as part of the project (executive, statewide, individual
airport, none). ANSWER
3: We will be expecting
individual airport reports. The KY Department of Aviation will be
responsible for combining the individual reports into a statewide plan. QUESTION
4. Can resumes for key
subconsultant staff be included? ANSWER
4: Yes, as allowed for
in the Instructions
for Response to Announcement Response to Announcement for
Engineering and Related Services Page 4(A-E):
Relative Experience of Key Project Team Members Include the resumes of the
project manager and up to 9 other key project team members, including sub-consultants , from page 2. Only include resumes for team
members with significant contributions to the project. (Additional resumes
may be allowed if indicated in the advertisement bulletin). Resumes may
include but are not limited to education and experience, applicable technical
training, personal photograph, responsibility for similar projects,
familiarity with geographic area and resources, and special or unique
experience. A total of 5 pages (A-E) are permitted for these resumes. 2009-06 Marshall/Trigg
Geotechnical Services QUESTION: Because of the complexity of
the project and the size of the contract given the schedule,
many will be forming teams, can the number of resumes be
increased to fifteen? ANSWER: KYTC will allow 3 additional
pages in the Page 4 Relative Experience of Key Project Team Members to
provide resumes of the project manager and up to 14 other key project team
members, including sub-consultants, from page 2. A total of 8 pages
(A-H) are permitted for these resumes. 2009-06 Marshall/Trigg Geotechnical Services QUESTION: In checking on water depths for the proposed new structure on
RESPONSE: The schedule of water level changes throughout
the year is referred to as the “guide
curve”. A copy can be found at
http://transportation.ky.gov/progperform/Bull%202009-06/Barkley%20Guide%20Curve.pdf
KYTC is planning to perform
drilling from May to July 2010. The final alignment has not
been selected yet and any information the Geotechnical Branch has on the
bottom of lake profile would be approximate. More detailed information will
be provided to the selected consultant when the information is available. 2009-06
Marshall/Trigg Geotechnical Services QUESTION: Bulletin
2009-06 requires the consultant in responding to address seismic expertise,
special laboratory testing certifications and barge drilling. To provided
adequate supporting documentation for the selection committee and KYTC
Geotechnical staff’s evaluation of the professional expertise of the
selection consultant can we have approval of additional pages to the new
Response Format? ANSWER: KYTC will allow 6 additional pages in the Page 7 Project Approach to provided adequate supporting documentation to address seismic expertise, special laboratory testing certifications and barge drilling required by the RFP. 2009-06
Marshall/Trigg Geotechnical Services QUESTION: Would you please share the names
of the firms that comprise the design team(s) for the two new bridges? ANSWER: In October 2006, Michael Baker, Jr., Inc. was selected for Bridge
Type Study and Final Design for New Bridges over Barkley &
New Bridges over QUESTION: Are the geotechnical firms who
performed the previous studies excluded from doing additional work? ANSWER: No firms are excluded from submitting a response to announcement. QUESTION: Will any of the firms associated with
the design team(s) be excluded from priming or supporting this contract? If
so, would you please name the firms? ANSWER: No firms are excluded from submitting a response to announcement.
The selected geotechnical consultant will be expected to coordinate with the
Department and the bridge design team regarding scheduling and prioritization
of specific work tasks. QUESTION: Will DBE participation be required as part
of this contract? ANSWER: The following will be added to the
advertisement: Consultant team may include a DBE participation plan with
their response to announcement. An additional page will be allowed with the
Project Approach (page 7) in the response to announcement to convey this
plan. A maximum of 2 points will be considered in the evaluation factors for
the DBE participation plan. 2009-06
Marshall/Trigg Geotechnical Services CLAIRIFICATION: Two of the geotechnical reports referenced in the
bulletins have were not uploaded and available at
the time of the posting of the bulletin on Tuesday, May 12th. (These
are SA-022-2007 & SA-023-2007 - the most recent and relevant
reports.) These
reports have now been uploaded and are available. If still having problems try http://transportation.ky.gov/progperform/Bull%202009-06/SA-022-2007.pdf
& http://transportation.ky.gov/progperform/Bull%202009-06/SA-023-2007.pdf
2009-06 STATEWIDE AIRPORT PAVEMENT MANAGEMENT QUESTION:
Regarding the subject
bulletin for Statewide Airport Pavement Management, under the instructions
for response, page 1, it requires certification that the consultant be prequalified to submit for the work. It also
states that any subs should also certify if they are prequalified. Is
it a requirement then that all subs be prequalified, or that if they are,
they must certify that they are? ANSWER:
At least on Consultant Firm
on the team must meet the prequalification requirements. It is not
required that all Consultant Firms on the proposed team be prequalified. 2009-06 STATEWIDE
AIRPORT PAVEMENT MANAGEMENT QUESTION: The first page of the bulletin in the section
"Purpose and Need", the sentence ends in "...and the". Is
there a missing requirement that should be noted here? ANSWER: Purpose and Need contained a printing error.
The full purpose and need should read: QUESTION:
In evaluation factor number
9, points are given for "Consultant's ANSWER: Selection committee members will use their own
discretion in applying the points for “Consultant's
Kentucky Office”. 2009-06 STATEWIDE
AIRPORT PAVEMENT MANAGEMENT QUESTION:
Does the department desire the
selected consultant to provide reports for each airport including detailed
maintenance plans and estimated capital improvement funding needs, or does
the department desire to make these determinations in house based on data
provided in the APMS software? ANSWER:
The KY Department of Aviation
does require maintenance plans based on the firms experience and the results
of the APMS analysis. This should include cost estimates for the
recommended action at each airport. It will be up to the Department of
Aviation to prioritize the airports and projects based on this information. QUESTION:
Does the department
anticipate that pavement cores, nondestructive testing (fall weight deflectometer), or engineering analysis to determine
pavement load carrying capacity will be included in the base scope of
services, or would these be considered as additional services to be performed
if needed? ANSWER: No structural/load bearing analysis will be
required as a part of the initial project scope. If it is decided that
these services are required, they will be considered "additional
services".
|
|