TENTATIVE – SUBJECT TO CHANGE
DRAFT - PUBLIC INVOLVEMENT PROGRAM - SCHEDULE OF ACTIVITIES
I-66 SOMERSET TO LONDON
PHASE 1A (CORRIDOR REFINEMENT)
|
Date |
Time Line |
Activities |
|
10/29/2002 Tuesday |
0 |
Citizens Committee #1
|
|
11/19/02 Tuesday |
+3 weeks |
Citizens Committee #2 (sub-committee breakout groups)
|
|
2/04/03 Tuesday
|
+10 weeks
|
(Includes Christmas and New Year holidays plus two weeks for peer review comments) Citizens Committee #3 (sub-committee breakout groups)
|
|
3/04/03 Tuesday |
+4 weeks |
(Includes two weeks for peer review comments) Citizens Committee #4 (sub-committee breakout groups)
|
|
4/01/03 Tuesday |
+4 weeks |
Newsletter No. 1 (Preparation, review and mailing) |
|
4/15/03 Tuesday |
+2 weeks |
Citizens Committee #5 (Identification of possible alternatives)
|
|
4/22/03 Tuesday |
+1 weeks |
Advertise date and location for Public Meeting |
|
5/13/03 Tuesday |
+3 weeks |
Citizens Committee #6 (Prepare for Public Meeting)
|
|
5/27/03 Tuesday |
+2 weeks |
Newsletter No. 2 (Preparation, review and mailing) |
|
6/10/03 |
+2 weeks |
Public Meeting |
|
7/01/03 Tuesday |
+ 3 weeks |
Citizens Committee #7 (Review Public Comments) |
|
7/22/03 Tuesday |
+3 weeks |
Citizens Committee #8 (Refine alternatives / prepare for Public Meeting)
|
|
8/12/03 Tuesday |
+3 weeks |
Newsletter No. 3 |
|
Initiate Phase 1B – Environmental Assessment & Preliminary Engineering |
||
|
8/26/03 Tuesday |
+2 weeks |
Public Meeting (if necessary) – Present the Three Recommended Alternates |
|
+4 weeks |
Citizens Committee #9
|
|
|
46 weeks |