The report for any given
Post-Construction Meeting may be accessed by simply clicking on the desired item number.
Post-Construction
Review Meetings for District 12 |
County/
Item No. |
Route |
Date |
Project |
Description |
|
Johnson Co. |
KY 1428 |
02/25/00 |
Hager Hill Connector from 250' east of KY
825 to US 23 |
|
Knott Co.
|
KY 89/KY 160 Intersection |
02/24/00 |
|
Intersection Improvement |
|
Knott Co. |
KY 89 |
02/24/00 |
|
Curve Revisions
|
Pike Co.
12-00310.01 |
KY 199 |
|
|
Grade/Drain/Surface |
Floyd Co.
12-00296.00 |
KY 114 |
01/18/01 |
|
Grade/Drain/Surface |
Martin Co.
12-01046.00 |
KY 292 |
01/18/01 |
Warfield-Louisa Rd. |
Bridge Replacement |
|
Johnson Co. |
US 23 |
11/12/96 |
|
Grade/Drain/Surface |
Pike Co.
12-00253.01 |
US 460 |
11/11/97 |
|
Bridge Construction
|
Pike Co.
12-00309.04 |
US 119 |
11/12/97 |
|
Grade/Drain/Surface |
Johnson Co.
12-00106.00 |
KY 302 |
12/19/95 |
|
|
|
Letcher Co. |
US 23 |
10/21/97 |
|
Grade/Drain/Surface |
|
|
|
|
|
|
|