The report for any given Post-Construction Meeting may be accessed by simply clicking on the desired item number.

Curve Revisions

Post-Construction Review Meetings for District 12

County/
Item No.
Route Date Project Description
Johnson Co. KY 1428 02/25/00 Hager Hill Connector from 250' east of KY 825 to US 23  
Knott Co.
KY 89/KY 160 Intersection 02/24/00   Intersection Improvement
Knott Co. KY 89 02/24/00  

 

Pike Co.
12-00310.01
KY 199     Grade/Drain/Surface
Floyd Co.
12-00296.00
KY 114 01/18/01   Grade/Drain/Surface
Martin Co.
12-01046.00
KY 292 01/18/01 Warfield-Louisa Rd. Bridge Replacement
Johnson Co. US 23 11/12/96   Grade/Drain/Surface
Pike Co.
12-00253.01
US 460 11/11/97  

Bridge Construction

Pike Co.
12-00309.04
US 119 11/12/97   Grade/Drain/Surface
Johnson Co.
12-00106.00
KY 302 12/19/95    
Letcher Co. US 23 10/21/97   Grade/Drain/Surface