June 6, 2001
Jim Rummage, P.E.
Chief District Engineer
District 9, PO Box 347
Elizaville Rd
Flemingsburg, KY 41041
Dear Mr. Rummage:
Subject: Bath County
I-64 Rehabilitation
Item No. 9-2005.00
Carter County
Item No. 9-0155.01
KY 1 Widening
Post-construction Review
Post-construction reviews of the subject projects were held on May 3, 2001 in the District 9 conference room with the following personnel in attendance:
Siamak Shafaghi C. O. Highway Design
James Simpson C. O. Highway Design
Diana Radcliff C. O. Operations
Ronnie Miller District 9, Construction
Joette Fields C. O. Highway Design
Robert Semones C. O. Highway Design
Katrina Bradley District 9, Construction
Larry Taylor District 9, Construction
Robert Trent District 9, Construction
Joette Fields C. O. Highway Design
Joey Hodskins J.M. Crawford & Assoc.
Arman Razavi C. O. Division of Traffic
Peter Shaffer District 9, Construction
The attendees reviewed the plans and the change orders occurred during the construction of both projects. A total of nine (9) change orders had been issued for these projects with two (2) change orders on the I-64 project pending approval.
The meeting was followed by on-site investigation of the project areas. The I-64 project in Bath County involved pavement rehabilitation of a section of the highway encompassing a distance of 7.2 km--MP 117.00 to 121.50. The Carter County project involved widening of KY 1 for a distance of 0.571 km from 0.2 mile south of I-64 north to AA Highway. The meetings dealt with issues pertaining to Grade, Drain, and Surface. The following is an account of the incurred change orders on each project.
Bath County: I-64 Pavement Rehabilitation
CHANGE ORDER NO. 1
As per the project phasing, the existing outside shoulder of I-64 was to be used to divert traffic. The existing shoulder was to be removed and replaced with full depth asphalt material to provide added stability. This change order was issued to set up the pay item for Asphalt Pavement Milling of the said shoulder area, which had been inadvertently left out from contract.
Contract time was not affected by this change order.
Increase $133,360.92
CHANGE ORDER NO. 2
This change order was approved to authorize the following changes;
Contract working days remained unaffected by this change order.
Increase $457,733.95
CHANGE ORDER NO. 3
This change order added additional excavation (104,000.00 CU M) of several cut slopes, where the earth material consisting of shales and limestone, was highly unstable and presented a significant safety concern to the travelling traffic with regard to rock falls. This change order included all items such as Clearing and Grubbing, Maintenance and Control of Traffic, etc., necessary to stair-step and lay the unstable areas back in stable slopes away from the highway.
Contract time was not affected by this change order.
Increase $1,714,933.00
CHANGE ORDER NO. 4
This change order was approved to modify the contractors approved replacement bearings for the I-64 Bridge over Kendall Spring Road. Added in this change order were also temporary pavement markers Type IV needed for proper one-lane traffic delineation through the four (4) sets of bridges located on this project. This change order added Special Seeding Crown Vetch on slopes steeper than 3:1. This item had been set up in the plans without pay items. Additional items left out from the plans were guardrail bridge end connectors Type A-1 and guardrail terminal section No. 1. These oversight items are indicated in Standard Drawings RBC-001-07 and RBB-002-07.
Contract time remained unaffected by this change order.
Increase $25,663.79
CHANGE ORDER NO. 5
This change order was approved to provide additional leveling and wedging in order to pave the roadway and shoulders according to the profile grades specified in the plans. This change was necessary as the depth of asphalt in certain areas was up to 26". Included in this change order was an agreement with the contractor to add twenty (20) working days to the contract. This time extension settled all claims by the contractor regarding contract time through the issue date of this change order.
Contract time extended by twenty (20) days.
Increase $769,275.00
CHANGE ORDER NO. 6
Due to numerous change orders, this project was prolonged through the construction season and had to be opened to traffic. Consequently, a solid white stripe used to delineate traffic during a lane closure was removed by means of a milling machine. This was necessary to safely accommodate eastbound and westbound traffic throughout the winter months. This change order was approved to reimburse the contractor for pavement striping removal.
Contract time was not affected by this change order.
Increase 410,960.00
CHANGE ORDER NO. 7
This change order was to request approval for reconstruction of existing Drainage Box Inlets within the safety zone. Extension of a 1050-mm pipe and construction of a Sloped & Flared Box Inlet/Outlet was also included in this change order. The aforementioned drainage work alleviated the need for guardrail.
Contact time was unaffected by this change order.
Increase $10,472.63
CHANGE ORDER NO. 8
This change order was submitted to implement cut slope revisions located at eastbound Sta. 26+000 to 26+360 and westbound Sta. 26+080 to 26+280. This action was necessary because of a major safety concern due to the precarious nature of slope material in the project area predominately consisting of highly weathered shales and limestone. This change order included all items necessary to perform the work including maintenance and control of traffic, drainage and erosion control, and excavation.
Contract working days were extended through the effective completion date of the project on August 31, 2001.
Increase $1,261,109.00
The contractor for this project was The Walker Company of Kentucky, Inc.
Original contract amount $12,776,302.59 *
Total approved change orders.. . ..$627,718.66
Total revised contract amount $13,404,021.25
* Does not reflect change orders 7 & 8
* * *
Carter County: KY 1 Widening
CHANGE ORDER NO. 1
This change was issued to implement the following changes and/or modifications;
Eight (8) additional working days were allowed by this change order.
Increase $111,637.05
The contractor for this project was Judy Construction Co.
Original contract amount $3,683,253.76
Total approved change orders.. . $111,637.05
Total revised contract amount $2,057,603.71
The attendance of all participants in this post-construction review is greatly appreciated. Please submit any additional comments to this office by June 25, 2001. All comments will be reviewed and disseminated to the appropriate personnel for consideration.
Sincerely,
J. M. Yowell, P.E.
State Highway Engineer
By: Gary Sharpe, P.E.
Director, Division of Highway Design
JMY:GS:SS
cc: M. Hacock. G. Sharpe D. Kratt J. Simpson D. Hite R. Divine J. Stone
J. Mettille S. Goodpaster D. Newman E.Wisniewski C. Knowles S. Cornett
Judy Construction Co The Walker Co. of Ky, Inc