August 31, 2001
Edward H. Merryman, P.E.
District 2
1840 North Main Street
PO Box 600
Madisonville, KY 42431-5003
Dear Mr. Merryman:
Subject:
Western Kentucky Parkway
STPR 2-1 (15)
FD04 089 9001 055-060
Item No. 2-2006.00
Post-construction Review
Post-construction review of the subject project was held on June 19, 2001 in the District 2 conference room with the following personnel in attendance:
Robert Semones C. O. Highway Design
Siamak Shafaghi C. O. Highway Design
T. C. Chambers District 2, Construction
Tim Layson District 2, Construction
Mike Joyner District 2, Design
Pam Kolze District 2, Design
Jeff Sutton District 2, Design
Steve Nicholson District 2, Design
Sherri Greenwell C. O. Operations
The attendees reviewed the plans and the change orders incurred during the construction of the subject project. A total of five (5) change orders had been issued for this project. The meeting was concluded with an on-site investigation of the project area. The project involved pavement rehabilitation of a section of Western Kentucky Parkway from IC Railroad Bridge at MP 55.52 to MP 59.85 for a total of 4.33 miles. The meeting dealt with issues pertaining to Guardrail, Edge Drain, and Surface. The following is an account of the incurred change orders.
CHANGE ORDER NO. 1
This change order was approved in part to upgrade the planned erosion control scheme by using Erosion Control Blanket in the entire area of the median. This change was deemed necessary in order to overcome the recurring difficulty in achieving seed germination. This change yielded the desired vegetative cover. This change order also added Temporary Bridge End Connectors Type A and C. These items which were not included in the plans, were needed to protect the bridge ends that would otherwise be exposed when traffic would be crossed over in the opposing direction. Other appropriate ancillary items such as temporary guardrail and end treatments were also added as required. All end treatments became the property of the Department after removal and were delivered to Muhlenburg Maintenance Facility.
An extension of the contract working days was not noted in this change order.
Increase $38,611.70
CHANGE ORDER NO. 2
This change order was issued to perform the following changes and/or modifications;
An extension to the working days was not addressed in this change order.
Increase $11,114.50
CHANGE ORDER NO. 3
This change order allowed the use of Cedar Rapids Remix paver in lieu of the MTV on the remaining section of the project from MP 56.03 to MP 59.85. This change was recommended by the Resident Engineer and resulted in approximate savings of $800,000.00. This change order also added additional quantities of Pavement Removal from the shoulder areas. This work was originally set up. However, quantities were not included in the plan summary. This change order also allowed additional quantities of PCC Pavement Repair to repair the concrete, which had deteriorated in the areas where traffic had been shifted throughout the winter months.
Eight (8) additional working days for Change Order 1 and Change Order 2 were allowed by this change order.
Increase $216,315.00
CHANGE ORDER NO. 4
This change order was issued to perform the following changes and/or modifications;
Fifteen (15) additional working days were allowed by this change order. Nine (9) days were for not allowing the contractor to work because of Memorial Day and Independence Day holidays. Five (5) days were allowed per the TEBM for Construction to avoid changing the plant over during the surfacing operations. And one (1) day was allowed for the actual work done.
Increase $39,690.00
CHANGE ORDER NO. 5
This change order was issued to perform the following changes and/or modifications:
No additional working days were allowed by this change order.
Decrease $135.91
Comments
The contractor for this project was Road Builders, Inc.
Original contract amount $14,474,732.10
Total approved change orders ..$305,595.29
Total revised contract amount $14,780,357.39
Change orders resulted in an increase of 2% in the total project cost.
The attendance of all participants in this post-construction review is greatly appreciated. Please submit any additional comments to this office by September 24, 2001. All comments will be reviewed and disseminated to the appropriate personnel for consideration.
Sincerely,
J. M. Yowell, P.E.
State Highway Engineer
By: Gary Sharpe, P.E.
Director, Division of Highway Design
JMY:GS:SS