August 18, 2000
Mr. Jim Rummage, PE
Chief District Engineer
District 9
Elizaville Road
P. O. Box 347
Flemingsburg, KY 41041
Subject: Rowan County
I-64 Rehabilitation
KY 32 Widening
PCN 960839 CH 961184
Post-construction Review
Dear Mr. Rummage:
A post-construction review on the subject project was held on May 17, 2000 in the District 9 conference room with the following personnel in attendance:
Siamak Shafaghi C. O. Highway Design
Robert Semones C. O. Highway Design
Deanna Harris District 9, Construction
Katrina Bradley District 9, Construction
Steven Hendersdon C. O. Geotechnical Branch
James Simpson C. O. Highway Design
Phil Banton Woolpert Engineering
Peter Shaffer District 9, Construction
Diana Radcliffe C.O. Operations
Gary Back Hinkle Contracting Co.
B. R. Miller District 9, Resident Engineer
Tom Ralston Hinkle Contracting Co.
Rick Omohundro District 9, Pre-Construction
The attendees reviewed the project plans and construction Change Orders. Nine (9)
change orders had been issued for this project. The meeting was followed by an on-site investigation of the project area. This meeting dealt with issues pertaining to Break, Seat, and Overlay (asphalt) of I-64 from Bullfork Road and Creek overpass extending east to 1.118 miles east of KY 32 Bridge. This meeting dealt with issues pertaining to Grade, Drain, and Surface for a distance of 3.65 miles. This project also involved reconstruction of KY 32 for a distance 0.33 mile to add a continuous turning lane which was accomplished on a "proposal" basis. Plans for this project were developed from field and arial surveys. The following is an account of the change orders and the reasons for the occurrence.
CHANGE ORDER NO. 1
This change order was approved to replace two (2) diesel powered Message Sign with two (2) solar powered units as per Design Memo 19-96. The said units became the property of the Department.
No additional working days were allowed by this change order.
Increase $15,000.00
CHANGE ORDER NO. 2
This change order was approved to authorize the following actions;
Twenty (20) additional working days were allowed by this change order.
Increase $88,816.67
CHANGE ORDER NO. 3
This change order was issued to authorize the following activities;
Fifteen (15) additional days were allowed by this change order.
Increase $134,831.26
CHANGE ORDER NO. 4
This change order was approved to implement addition of a continuous turning lane on KY 32. This change involved reconstruction of KY 32 for a distance of 0.33 mile beginning at Sta. 43+00 and ending at Sta. 60+50, and comprised of all items necessary, including utility relocations, to construct the turning lane.
Fifty (50) separate working days were established by this change order based on an agreement between the Department and the contractor.
Increase $983,154.97
CHANGE ORDER NO. 5
This change order pertained to the widening of KY 32 and was approved to use a Quick Valve to make the switch from the old waterline to the new. This was paramount to ensure the water supply to the city and a hospital that were on the same service line, would not be interrupted. This procedure requested by the City of Morehead, required special knowledge and equipment provided by a sub-contractor.
Three (3) additional working days were allowed by this change order with respect to the construction of KY 32.
Increase $9,956.00
CHANGE ORDER NO. 6
This change order was issued for the emergency repair of westbound shoulder pavement. The westbound traffic on I-64 utilized a partial width of the shoulder as a driving lane, which caused excessive pavement failure posing a serious hazard to the traveling public. The emergency repair required total removal and replacement of 1600 ft. of feet pavement which was deemed necessary by the Department. This work was performed at night and required closing the westbound lane of I-64 and detouring the traffic via US60. During the course of construction, a 60-foot section of woven wire right-of-way fence located between the eastbound and westbound Bullfork Bridge, Triplett Bridge, and the Bridge over KY 32, was inadvertently damaged. The right-of-way fence was repaired or replaced as appropriate.
This change order resulted in a net increase of six (6) working days.
Increase $20,109.70
CHANGE ORDER NO. 7
This change order was related to the widening of KY 32 and was issued to reimburse the Morehead Utility Plant Board for relocating their facilities during roadway construction in accordance with the requirements of KRS 177.053.
No additional working day was necessary for this change order.
Increase $1,193.37
CHANGE ORDER NO. 8
This change order applied to the widening of KY 32. It was implemented to construct a modified paved ditch and lower a Drop Box Inlet to facilitate proper drainage at the intersection of KY 32 and Ramp A (westbound I-64 off ramp). This action was deemed the best remedy for a drainage problem where Ramp A intersected I-64. Also included in this change order was filling and capping of two Drop Box Inlets which were encountered during the construction of KY 32.
Ten (10) additional working days were allowed by this change order with respect to
the widening of KY 32.
Increase $8,602.15
CHANGE ORDER NO. 9
This change order was issued per the direction of the Division of Traffic to construct traffic signals at the intersection of KY 32 and the I-64 eastbound and exit ramps to alleviate safety concerns. This change order deleted several items that were not utilized on this project. Those items consisted of Asphalt Wedge Curb, Fertilizer 20-10-10, Standard Header Curb, a Curb Box Inlet, and Adjusting Guardrail.
Forty one (41) additional days were allowed by this change order to complete the project post the addition of a turning lane on KY 32.
Increase $13,773.95
The contractor for this project was Hinkle Contracting Corporation.
Original contract amount……………………$9,205,701.12
Total approved change orders..…………….…$1,275,438.07
Total revised contract amount………………$10,481,139.19
The attendance of all participants in this post-construction review is greatly appreciated. Please submit any additional comments to this office by July 7, 2000. All comments will be reviewed and disseminated to the appropriate personnel for consideration.
Sincerely,
J. M. Yowell, P.E.
State Highway Engineer
By: Gary Sharpe, P.E.
Director, Division of Highway Design
JMY:GS:SS
cc: C. Raymer D. Kratt J. Simpson D. Hite R. Divine S. Cornett J. Stone
J. Mettille S. Goodpaster D. Newman E.Wisniewski C. Knowles Woolpert LLP
Hinkle Contracting Copr.