December 9, 1996
Mr. Paul E. Toussaint
Division Administration
Federal Highway Administration
P. O. Box 536
Frankfort, Kentucky 40622
Dear Mr. Toussaint:
SUBJECT: Kenton/Campbell Counties
I-275, Cincinnati Bypass
FD52 059 0275 078-083 108 C
FD52 019 0275 073-078 075 C
IM 275-9(84) 14
A post-construction review was held on the subject project on November 15, 1996, in the District 6 office. The following personnel were in attendance:
Daryl Greer C. O. Highway Design
Robert Semones C. O. Highway Design
Paul Doss Federal Highway Administration
Jim Peace District 6, Construction
Robert Farley Federal Highway Administration
George Hoffman District 6, Pre-Construction
David Kratt C. O. Design
David Fultz District 6, Resident Engineer
Dave Heil E.A. Partners
Les Haney…………………………. E.A. Partners
Richard Guidi…. District 6, Design
The attendees reviewed the project plans, maintenance of traffic, and construction change orders. This post construction meeting dealt with issues pertaining to a pavement rehabilitaion project. The project was approximately 6 miles long , 2 lanes each direction.
The following issues were discussed:
The following change orders were discussed:
There have been eight change orders to date on the project.
CHANGE ORDER NO. 1
This change order was issued to modify the traffic control scheme The original pavement rehabilitation was set up in two sections. The original traffic control was setup to maintain eastbound traffic on eastbound side and westbound traffic on westbound side while performing work in the interior median. A value engineering proposal was submitted by the contractor to provide a new maintenance of traffic scheme assuming the project as one section. The ultimate maintenance of traffic allowed the existing traffic to be transitioned to one side allowing a larger work area. This method provided easier access for construction equipment than the original M.O.T scheme and eliminated night time paving.
Savings $373,641.41
CHANGE ORDER NO. 2
This change order was necessary to implement the contractor’s "Value Engineering" proposal for using an automatic dowel bar inserter. The proposal was reviewed and accepted by District and Central Office personnel. The inserter was utilized on the two outside lanes of pavement eastbound and westbound the length of the project. This change order also allowed for changing the bond breaking coating on the dowel bars to facilitate the machine provided the substitute coating used meets KDOT materials approval.
Savings $32,569.60
CHANGE ORDER NO. 3
This change order provided signing for a right lane drop on southbound I-75 just south of the Kyles Lane Overpass. Although included, this change order did not apply to the subject project.
Additional Cost $7,000
CHANGE ORDER NO. 4
This change order was necessary to upgrade the existing I-275/Ky. 16 interchange as directed by District Office personnel in order to handle a large increase in traffic volume anticipated due to development in the area. This change order reflects adding turning lanes and removing the median between stations 27+00 and Sta. 74+00 of Ky. 16 . This change order could have been eliminated if this item was considered in the initial rehabilitation project.
Additional Cost $423,202.62
CHANGE ORDER NO. 5
This change order was necessary to delete the contractor’s "Value Engineering" proposal for using an automatic dowel bar inserter. The proposal as described in change order #2 was tried but failed to work properly. The cost offsets the fee in change order #2
Additional Cost $32,569.60
CHANGE ORDER NO. 6
This change order reflected the conversion of headwalls from cubic yard to each. A volume would not have to be calculated when specified by "each" quantity. Mechanical Stabilization was also omitted at the request of the District which resulted in subgrade preparation. The cost of the subgrade preparation was thought to be part of the original cost of cutting to grade. Guardrail end treatments were changed from Type 3 to Type 1. Using the Type 1 guardrail end treatments resulted in the elimination of additional pipes and drainage boxes. This change order also provided for overruns in estimated shoulder pavement removal.
Additional Cost $93,620.67
CHANGE ORDER NO. 7
This change order addressed the lighting during phases of construction. A note on the original plans specified that the existing lighting would not be disturbed. Due to washing and erosion of the existing earth slopes most of the existing conduit was exposed and deteriorated.
Due to construction and excavation of grades the existing conduit and junction boxes had to be disturbed thus resulting in Change Order # 7. The lighting on pavement rehabilitation jobs to be
given more consideration during the design phase. Once the grade was in place the earth slopes covered the light standards at some locations. This creates a traffic hazard since no guardrail was placed in front of the light standards.
Additional Cost $23, 963.72
CHANGE ORDER NO. 8
This change order reflects the additional pipes and drop boxes needed to facilitate drainage of existing ditches. Cut slopes and benches had to be cleaned also.
Additional Cost $335, 875.00
A site visit followed the office review. The project appeared well constructed. It was suggested by Mr. Bob Farley that delineators at edge drain outlets be removed. This would provide a better clear zone for mowing equipment.
The original contract amount was $24,997,057.51. Approved change orders to date are $682,516.67 for a total revised amount of $25,679,574.17 . There are a few minor items for Central Office that have not been included at this time.
The attendance of all the participants in this post-construction review is greatly appreciated.
Sincerely,
J. M. Yowell, P.E.
State Highway Engineer
BY: John B. Sacksteder, P.E.
Director, Division of Highway Design
JMY:JBS:rts:pcr3-96.doc
cc: Post-construction Review Participants
Charles Raymer
FHWA File
Design File
J.E. Kearnes
J. Stone
P. Gravely
S. Cornett
S. Goodpaster
R.A. Yeager
C.L. Meyers
W. Crace
G. Sharpe