June 8, 2000
Mr. William Monhollon, P.E.
Chief District Engineer
District 5
977 Phillips Lane
P. O. Box 37090
Louisville, KY 40233
Subject: Shelby County
Welcome Center
IM 64-2(144) 28
Post-Construction Review
Dear Mr. Monhollon:
A post-construction review was held on the subject project on Tuesday, March 7, 2000 in the Central Office Conference Room. The following personnel were in attendance:
R.R. Meyer D-5, Construction
Joette Fields C. O. Highway Design
Siamak Shafaghi C. O. Highway Design
George Best C.O. Highway Design
Robert Semones C. O. Highway Design
Nasby Stroop C.O., Construction
Bernie Roach C.O., Construction
Spencer Sullivan. KDOT, Materials
Robert Farley.. FHWA
Carol Goes.. Balke Engineers
Gilbert Newman.. Balke Engineers
Karim Siahkoohi.. Balke Engineers
Robert Bicknaver. Balke Engineers
James Woody.. C.O. Operations
John Smoot.. C.O. Operations
P. David Cornett.. C.O. Operations
The attendees reviewed the project plans and construction Change Orders. There were eight (8) Change Orders on the project. This post-construction meeting dealt construction of the Shelby County Rest Area. This meeting dealt with all issues pertaining to the construction and maintenance of the building, items in the building, landscaping, drainage and other items that needed to be discussed before the construction of other proposed Welcome Centers.
The following Change Orders were discussed:
CHANGE ORDER NO. 1
At the request of the Simpsonville Sewer District, it was agreed to increase the proposed sewer line from 8 inch to 10 inch. This increase in diameter was requested due to future expansion in the area. In addition, four (4) foot stubs will be built from the manholes at the ending stations to provide a tie in location for future expansion. The solid rock near the area of the manholes will be excavated by mechanical and blasting means, as appropriate, to prevent damage to the system by future construction. Simpsonville Sewer District reimbursed the state for this additional cost.
Due to existing field conditions, it was determined that a 54 inch utility tunnel should be used for the utility crossings under I-64 in lieu of the two 24 inch bores as shown on the plans. The tunnel would have better constructibility, will allow for future servicing and/or expansion of the lines, and can be provided at no additional cost to the State. The 54 inch tunnel was bored and jacked thus eliminating the need for open trenching as originally designed for the 24 inch bores.
The Utility Office in District 5 requested the contractor leave an existing access road in place. This access road provides entry to the work site behind the existing west bound rest area. It was decided to leave the access road in place for future maintenance. It was agreed to place Crushed Aggregate Number 2 on the road during and after completion of the work. It was agreed to pay the same price as that for crushed stone base.
Cross sections indicated that the finish elevations between Baseline #1 and Baseline #2 are within solid rock. Central Office Division of Construction has stated that a minimum of 30 inches is needed to sustain the landscaping. It was agreed to undercut these areas. The areas will be drained with the use of perforated pipe, which will discharge into drop box inlets along the right of Baseline #1 and the left of Baseline #2 or out of perforated pipe headwalls.
Material under the pipe at Sta. 28+52.557 was determined to be unsuitable for backfill placement. It was agreed to undercut this area and backfill with stone.
The Utility Office of District 5 had made revisions to the utility plans since the project was let for bidding. These changes include changes in the alignment of the water and sewer lines and the addition of three manholes, Type B at pipeline stations 1+30, 3+72.67, 7+92 to provide for future maintenance.
It was suggested by Operations that a minimum of 36" soil would be better to sustain the landscaping.
Increases $410,792.70
Decreases. $342,330.00
NET INCREASE. $68,462.70
CHANGE ORDER NO. 2
Construction of the exit and entrance ramps required removal of the right shoulder in the east bound direction. The plans called for a Lane Closure Case III to be used for adequate traffic control. Due to the probability of large traffic delays involved with a lane closure on a high volume interstate, it was agreed to use a Shoulder Closure Case II and install Temporary Concrete Median Barrier Wall with a crash worthy end treatment along the right shoulder. This served to protect the work zone and allow for two lanes of traffic to be maintained. This was accomplished by shifting the eastbound lanes to the left, using the left median shoulder. The traffic volumes were higher than those anticipated. It was suggested to have current traffic counts for this type of construction.
Suggestions from the meeting:
Due to the nature of the work involved for installing and removing the Concrete Median Barrier Wall, a lane closure was necessary. The Contractor did not bid Item No. 72, "Maintain and Control Traffic", for the short duration that the lane closure would be in place. The barrier wall had to be removed and installed twice during this operation. Therefore, the contractor was due additional compensation for maintaining and controlling traffic. Additional compensation was given to the contractor for placing a variable message board in the eastbound lanes to provide advanced warning of the lane closure.
In order to facilitate drainage of the sub grade material in the existing east bound lanes of the I-64 through the shoulder widening being performed and for construction of the exit and entrance ramps, the district office and FHWA determined that a seven inch drainage blanket layer of Crushed Aggregate #57’s was needed. As a result of the additional thickness of drainage blanket, the sixteen inch layer of crushed stone base in the pavement design was reduced to nine inches. Since the material costs are the same and construction methods are identical, the unit price of $14.00 for crushed stone base was accepted for the use of crushed aggregate #57s.
It was requested to set up edge drains throughout the project limits. This may be an item to investigate on future welcome center sites.
The plans indicated removal of 450 linear feet of guardrail at Rt I-64 Sta. 1055+25 to Sta. 1059+75. However, the area behind the guardrail is not to be improved and must be protected. It was agreed to leave the guardrail in place and upgrade the end treatment from Type 4 to Type 4A.
The Operations Office in District 5 had requested additional drainage items to improve the drainage and prevent problems currently being faced at the facility on I-65 south bound in Bullitt County. This work consisted of installing french drains around the building to improve subsurface dewatering.
An increase of 10 Working Days was allowed for this Change Order.
Increase $200,266.26
CHANGE ORDER NO. 3
In order to provide a more environmentally friendly material, a Change Order was needed to allow the Contractor to use Hydro-Stik as an adhesive material for seeding and protection. Specifications allow this as an alternative. There was no change in cost incurred for the replacement.
Due to the inadequacy of the 4 inch water service to handle 259 gallons per minute demanded by the fire protection system from the "tee" between water line stations 8+44.49 to 20+33 near the Welcome Center main building, it was agreed to increase the size of this water service to 6 inches. This increase includes all necessary changes to accessories involved with the water service as needed. The quantity for contract item "gate Valve – 4 inch" will be decreased accordingly. The quantity for contract item "Ductile Iron Pipe –4 inch" will be deducted from the original quantity to leave 620 linear feet which was placed for water service to the existing Westbound Rest Area. The supplemental unit price for "Modify Air Release Valve w/ Vault" will be needed to increase the size of an existing valve with vault from 4 inches to 6 inches. Also, the contractor is entitled to a restocking charge associated with materials already ordered that are no longer useful. Further, the Department will receive 4 inch casing spacers already on site which cost the contractor $1,371.38 and can not be restocked since they are no longer useful to the supplier.
Due to the fact that the materials and quantities do not appear on the plans, it was agreed to install water, sewer, electric, and telephone service lines from the Welcome Center Main Building to the Vending Building. This needs to be checked for future welcome centers.
In order to remove water from the traveled ways (sidewalks), it is agreed to install yard drains around the building and landscape areas associated with the Welcome Center. These Drains will consist of Drop Boxes and 8 inch Sewer Pipe and one headwall to be field located by the Resident Engineer. The headwall will be paid at the contract unit price for "Concrete – Class A". In addition, connections to Drop Box Inlets at the parking lots will have to be completed using drilled cores.
There was some concern discussed at the meeting that yard drains may be a maintenance problem in the future. It was suggested that other options be investigated for yard drainage applications.
An increase of 3 Working Days was allowed for this Change Order.
Increase $46,231.65
CHANGE ORDER NO. 4
Due to an error in the project plans, it was agreed to increase the amount of Roadway Excavation for this project to reflect actual totals encountered in the field. The corrected plan sheets are on file in the Resident Engineer’s office. This increase also includes totals to be encountered to complete guardrail installation and removal.
In order to provide proper landscape conditions and drainage, it was agreed to raise the Drop Box Inlet Type 3 located at Station 26+50 of Baseline #2. This work will require pouring an additional box on top of the existing box.
In order to provide fire-fighting capability at the Welcome Center, it was agree to install a fire hydrant adjacent to the main building. This work will also require an additional 6-inch gate valve to be installed at the contract price for "Gate Valve ‘ 6 inch" established in Change Order #3.
This Change Order permits the use of performance grade asphalt binders conforming to Section 806.06 of the Supplemental Specifications.
In order to provide proper facilities in the main building, it was agreed to install stairs and a handrail in the mechanical room to provide access to the overhead storage area, widen the writing surface of the front desk from 8 inches to 24 inches. It was further agreed to provide full length hinges on the main doors and vestibule doors leading into the lobby area, and to install additional electrical receptacles in the lobby area.
In order to cover costs incurred by the Contractor to upgrade the water line from 4 inches to 6 inches in the meter vault located at water line Station 11+00, it was agreed to establish a supplemental item to reimburse the contractor.
In order to provide a counting device to monitor the use of the Welcome Center, it was agreed to install counting loops on the off ramp at a location designated by the Resident Engineer. The Department will furnish the cabinet housing the device.
An increase of four Working Days was allowed for this Change Order.
Increase $81,033.93
CHANGE ORDER NO. 5
A field review has determined that, in order to obtain and achieve the desired landscaping performance, it was agreed to make various substitutions for plants and trees proposed for this project. Also, due to problems of availability of certain species, substitutions for these plants will also be made. It was agreed that the substitutions will be made at no additional cost to the Department and that all the Specifications and Guarantees will apply to the substitutions.
For aesthetic purposes, it was agreed to increase the quantity of Pin Oaks to be planed at this facility by a total of five (5) trees.
As located in the Initial Landscaping Final Inspection Report for the above referenced project, it was agreed to replace one Bottlebrush Buckeye that was field damaged. It was also agreed to apply Slow Release Fertilizer to all plants in the Welcome Center as set forth in the Initial Landscaping Final Inspection Report. The Report also stated that Pine Bark Mulch would be added to mulch beds due to field damage.
It was agreed to apply a heavier seeding rate to the infield area at the Welcome Center using 250 lbs. of seed as opposed to the required rate listed in the Standard Specifications for Road and Bridge Construction.
The quantities listed in the Project Proposal do not reflect the area required for Seed and Protect method II upon removal of the old Eastbound Rest Area. It was agreed to increase this quantity by the necessary amount.
Comments:
Contract Working Days were unaffected by this Change Order.
Increase $9,764.55
CHANGE ORDER NO. 6
It was necessary to install a Lighting Contractor to enable the ramp lighting to automatically engage using a photo electric eye.
It was agreed to construct an office to be utilized by Motor Vehicle Enforcement inside the main building.
In order to comply with ADA codes it was necessary to install steel handrails for the stairs in the rear of the main building. Originally, wooden handrails were specified.
It was agreed to install diaper-changing tables in one stall of each restroom located in the main building.
It was agreed to install permanent signs for informational purposes at various locations on this project and delineators for guardrail near off-ramp to Eastbound I-64.
It was agreed to install a new manhole hatch at the existing Westbound Rest Area to allow for greater ease for maintenance. This item shall be a non-participating item.
It was agreed to install bird screens around the lights in the top of each gazebo shelter.
It was agreed to install a water line to be used for a coffee machine in the Vending Building. This item shall be a non-participating item.
It was agreed to install lumber around all of the landscaping stone located at the main building. This border will enable the stone to better stay in place in an effort to aid the french drains that are located underneath it.
It was agreed to connect the newly constructed water line from near the existing Westbound Rest Area to the water line serving the building. This item shall be a non-participating item. It was agreed that gazebos not be constructed at future sites.
Contract Working Days were unaffected by this Change Order.
Increase $16,944.76
CHANGE ORDER NO. 7
Actual field conditions indicate the need to undercut and refill various areas prior to completing subgrade work. It was agreed to increase the quantity of roadway excavation to perform this work.
In order to provide for proper drainage and erosion control, it was agreed to increase the quantity of various items necessary to perform this work.
In order to better accommodate pedestrians, it was agreed to increase the width of sidewalks along the back of the Main Building near the truck parking lot from 5 feet to 7 feet.
Actual field conditions indicate the need to increase quantities for crushed stone base and asphalt surfaces in order to complete these items according to the Project Plans.
In order to complete the installation of edge drains as established in Change Order No. 2 for this project, it is agreed to increase the quantities for the untreated drainage blanket and geotextile fabric type IV.
In order to properly complete installation of lighting as shown in the Project Plans, it was agreed to increase the quantity of trenching and backfilling.
In order to properly tie the proposed on-ramp and off-ramp into the existing interstate shoulder, approximately 1 foot of the shoulder shall be removed to a depth of approximately 4.5 inches. This area is to be refilled with bituminous material to eliminate a cold construction joint throughout the length of these ramps.
Due to a transferring error of bid items to the Bid Package, it is agreed to add a sign bridge attachment bracket as shown on Sheet 16I of the Project Plans.
In Accordance with Special Provision No. 46K located in the 1994 Edition of the Supplemental Specifications to the Standard Specifications for Road and Bridge Construction, it is agreed to provide a fuel adjustment to the Contractor.
Contract Working Days were unaffected by this Change Order.
Increase $91,962.63
CHANGE ORDER NO. 8
Actual field conditions indicate the need to increase quantities for mulch, bituminous material, and channel lining in order to insure that erosion is properly controlled.
Contract Working Days were unaffected by this Change Order.
Increase $5,457.60
Additional comments were as follows:
The following items were discussed and should be incorporated into ALL future rest area and welcome center building projects:
Project Statistics are as follows:
Contractor: Hall Contracting Corporation
P.O. Box 37270
Louisville, Kentucky 40233-7270
Original Contract Amount $4,086,062.50
Total Change Order Amount $ 520,124.00
Total Revised Contract Amount $4,606,186.58
The attendance of all participants in this post-construction review is greatly appreciated.
Sincerely,
J. M. Yowell, P.E.
State Highway Engineer
BY: Gary W. Sharpe, P.E.
Director, Division of Highway Design
JMY:GWS:rts
cc: C. Raymer S. Cornett D. Newman R. Divine D. Kratt
A. Johannes Jim Stone J. Mettille C. Knowles D. Hite
B. Sanders R. R. Meyer K. Villier Hall Contracting G. Best
SHELBY COUNTY WELCOME CENTER
POST CONSTRUCTION REVIEW
INTERSTATE 64, SHELBY COUNTY, KY.