Questions and Answers

​​​​​​​​​​​​​​​​​​​​​​​

  
  
County
  
Question
Answer
  
11-1328308Hardin
Could you please provide contact information for the following property owners:  Parcels 3,11,12,14?  CM Wade Estate, Gillian T Nicely, Jr, Patricia A Ragland, and Jeff Lewis, respectively.
PARCEL  3 - CM Wade Estate- Trustee – PNC Bank, NA, 500 West Jefferson, 5th Floor, Louisville, KY 40202,  502-581-2519.  PARCEL 11 - Gillian T Nicely, Jr.,  P.O. Box 476, Elizabethtown, KY 42701,  270-765-5030. PARCEL 12 (Patricia A Ragland) is currently in litigation.  Bidders should not contact the property owner at this time.  PARCEL 14 - Jeff Lewis, Et Al- Jeff and Roberta Lewis, P.O. Box 2853,  Elizabethtown, KY 42702, 270-268-1309.  Mike and Sheila Robey, 2466 West Rhudes Creek Road, Elizabethtown, KY 42701, 270-846-2777.  Gary and Pamela Hinton, 1628 New Glendale Road, Elizabethtown, KY 42701, 270-765-5597, 270-763-7978.  Terry and Kathryn Hinton, 1688 New Glendale Road, Elizabethtown, KY 42701, 270-765-5597, 270-763-7979.
8/10/2011 9:42 AM
11-4022101Warren
Is SMA the intended/correct mix design type for this job?
Revised Answer:
No, SMA will not be required.  An addendum will be posted to the website.
 
8/11/2011 12:25 PM
11-3365400Bullitt
With ADT's from 600 to 2170, is it necessary to have restricted hours on all these roads as shown in the traffic control notes?
Revised Answer:
The restricted hours are not necessary.  An addendum will be posted to the website.
 
8/9/2011 10:12 AM
11-2941107Trigg
There are no details concerning the barrier retrofit for call 107 Trigg except for a bid item.  Can you elaborate?
Item No.  0220
“Bridge Barrier Retrofit” is to be removed from this project.
 
8/12/2011 2:24 PM
11-1328308Hardin
A callout note on Sheet R9 directs the reader to “See Structural Drawing No. 25775 for Culvert Details”.  No such drawing is included in the project plan set.  Please clarify.
The structure is a three-sided Culvert.  The bid items are on the General Summary and the structural drawing No. 25775 is on sheet R101.
8/8/2011 1:56 PM
11-1037310Jefferson
What are the liner specifications on the texture for the precast sound wall panels?
See page 25 and 26 of 103 in the proposal.  Under Precast Portion Finish Requirements:  “The finish on all exposed concrete shall match the texture and finish on the existing sound wall on eastbound I-264 between Taylorsville Road and Breckinridge Lane.”  “Provide two samples of the precast concrete panels, a minimum of four feet by eight feet, cast using same form liners as proposed for production for the Department’s approval.”   Under Precast Panels:  …“Place form lining to assure that the grooves, lines, and striations are normal to joints and lined up with adjacent panels with no offset.”  
8/10/2011 11:04 AM
11-2303302Leslie
If we attended the pre-bid meeting for this project when it was in the July letting, do we have attend the pre-bid meeting for this month’s letting?
Yes, bidders must attend the meeting this month to bid.
8/8/2011 1:47 PM
11-2179300Campbell
KY 1996 is posted for weight limitations on either end (KY 1121 and KY 10).  Can you verify what bridges or culverts are subject to that limitation?
The KY 1996 Bridge over Stevens Branch 0.259 miles east of KY 1121 is posted for the following reduced weight limits: Type 1 Single Axle Truck, 16 Tons; Type 2 Tandem Axle Truck, 17 Tons; Type 3 Tri-axle truck, 19 Tons; and Type 4 Semi-trailer Truck 31 Tons.  
The other structures on the route are subject to the following weight limits:  Type 1 Single Axle Truck, 22 Tons; Type 2 Tandem Axle Truck, 27 Tons; Type 3 Tri-axle truck 34 Tons;  and Type 4 Semi-trailer Truck, 40 Tons, (5 or more axles).
 
8/15/2011 11:20 AM
11-2967100Whitley
Special Notes for Bearing Replacement Proposal pg 21 of 68 Section III. Construction Item “B” Contractors Jacking plan shall be designed to support 200% of DL @ 44 Tons & LL @ 34 Tons = 78 Ton x 200% = 156 Tons.  Would 150 Ton Jacks be acceptable?
Yes, 150 ton jacks would be acceptable.  However, the Contractor is still responsible for the structure and the jacking operations.
8/9/2011 9:47 AM
11-1331105Ohio
Why is there not a pay item for mobilization on this Electrical Lighting Project?
Department’s policy did not mandate the mobilization bid item.  Therefore, the bid item was not included.
8/9/2011 10:28 AM
11-1037310Jefferson
Is there a specific liner type and manufacturer?
The Department is not specifying a liner type or manufacturer.  The finish on all exposed concrete shall match the texture and finish on the existing sound wall on eastbound I-264 between Taylorsville Road and Breckinridge Lane.  
8/11/2011 1:29 PM
11-2967100Whitley
Is the 156 tons for each beam line or for all four beam lines per structure.
The 156 tons is for each beam line.
8/9/2011 9:44 AM
11-1328308Hardin
On structure drawing no. 25774, the plans for the interior piers for the above mentioned project the notes say that pre-drilling should only occur if bedrock is encountered and that there is a minimum depth of 10’ below the cap. Could you please verify what piles, or if all of them , will required predrilling and also if the total quantities are correct on the plans to get the 10’ minimum depth?
The Department is unable to verify which piles will require predrilling.  The boring logs on S4-S8 are included for the contractor’s information.  The quantity is an approximate quantity.  Final payment will be for the measured and accepted quantity.
8/11/2011 10:50 AM
11-2950401Harlan
what the scope of work is to be accomplished during the respective 4 hour and 10 hour closures discussed on Page 10 of 58?
It is up to the contractor to determine how best to use this time when the bridge is closed to complete work.
8/15/2011 2:55 PM
11-2941107Trigg
Pay items #0080, 0090 & 0010 do not match up with Page 36 of 101 in the Proposal.  I only see 2 each armored edges and 2 each of 2” joints.  Don’t see any 1” joints.  Please verify
There are 2 armored edges, two 2” joints, and a two 1” silicone joints.  See page 37 of 101 for details of armored edges and 1” joints at the approach.  
8/15/2011 1:13 PM
11-1328308Hardin
Note 1 on the general summary sheet (R2C) states that there is tree clearing necessary for sign visibility which is detailed on sheet T9.  I find no reference to this work on sheet T9.  Could you please clarify what this clearing entails?
The T9 reference on the summary sheet is a mistake.  It should say T14.  
8/15/2011 1:16 PM
11-1036301Hardin
The quantities for the Drilled Shaft rock and the drilled shaft common do match up for the above mentioned call between the schedule provided and the quantities given. Could you please confirm the total quantity of these items?
REVISED ANSWER:
The elevations on the schedule on sheet S12 are for design purposes.  Please see the “Drilled Shafts” note on page S3.  The plan quantities are an estimation.  Final payment will be for the measured and accepted quantity.
8/15/2011 3:37 PM
11-1328308Hardin
Concerning bid Item line #0940, item#20958ND, CAP-10 IN, Is this line Plastic or Ductile?  Will a Deadman be needed?
A deadman is not required.  As noted in the General Summary, the encasement pipe is steel.
8/16/2011 12:02 PM
11-2937106Whitley
Bid item line No 0070 is a "Temp Signal Multi Phase".  On page 29 of the proposal,  the "Special Note for Traffic Control”  says "…Provide, install, and maintain a temporary two-phase traffic signal.".  Does the job call for a multi-phase or a two-phase signal ?
The reference to the two-phase signal on page 29 is incorrect and does not apply to this project.  Bid item line no 0070 “Temp Signal Multi Phase” in the bid items is correct and what will be used on the project site.
8/15/2011 3:43 PM
11-1036301Hardin
Concerning bid Item  20509ED,  Blow Up/Relief Joint, is there a Typical Section for this bid item?
A Blow Up/Relief Joint Detail is shown on Sheet R90o.
8/16/2011 4:04 PM
11-1036301Hardin
Will the internal backfill at the retaining wall be paid for?
The cost of the internal backfill is to be included with the retaining wall bid item.
8/16/2011 1:51 PM
11-1036301Hardin
Also, this work will be in a curve section and other places have required running temporary barrier wall through the curve.  Will that be required on this job?
No, it will not be required.
8/15/2011 3:23 PM
11-1036301Hardin
The plans indicate constructing the median barrier wall on the US 31W Bypass from 176+00 to 235+00.  However, due to culvert and bridge pier construction, at least three gaps will have to be left in the wall, and those for quite some time.  Should temporary crash cushions be used in this area?  As there will be work in the median of the US 31W Bypass involving large excavations within 10’ of the travel lanes, shouldn’t there be temporary concrete barrier wall set up to protect the public, inspectors, and workers? 
Temporary barrier wall and temporary crash cushions will be added.  An addendum will be posted to the website.
8/15/2011 3:23 PM
11-2982407Jackson
On pages 10 and 12, hoeram use is extremely limited. Will the contractor be held to these guidelines?
 
Yes, the guidelines on page 10 and 12 are to be adhered to as stated in the proposal.
8/16/2011 2:41 PM
11-1330201Breathitt
Has the approach left of 1251+48.70 has been constructed by the previous contractor?
Yes, the roadway excavation on the approach road in the plans was to finish the approach but it was completed by the previous contractor and the location of the approach was changed which negates the quantity in the plans, the roadway excavation quantity for subject approach should be zero, the remaining quantities associated with the approach should be bid as is.
8/16/2011 8:11 AM
11-1036301Hardin
Concerning bid Item 02610 Retaining Wall-Gabion is there a size for these Baskets?
Per Standard Drawings length can be 6’, 9’, or 12’.  Plan quantity includes additional quantity for a ditch tie-in.
8/16/2011 4:05 PM
11-1036301Hardin
On call #301 Hardin Co Is there a perforated pipe summery?  Or a table that shows station numbers for where the UD outlets are located?
No perforated pipe underdrain summary is available.  Quantities and headwall types were determined based on outlet spacing of approximately 250’.  The successful contractor shall coordinate with Resident Engineer to determine appropriate outlet locations.
8/15/2011 3:38 PM
11-2941107Trigg
Pay item #0220, Bridge Barrier Retrofit, has no details of the retrofit.  Could this be provided?
Item No.  0220
“Bridge Barrier Retrofit” should not have been included in this project. An addendum will be posted to the website.
 
8/15/2011 1:14 PM
11-2973305Whitley
On Page 13 of 60 in the proposal, under Reconstructing Portals and Sway Frames, it says “Only one portal or sway frame span shall be reconstructed at one time.”  Does this mean (1) per SPAN  or  (1) for the entire Bridge?
Reconstruct one (1) per span.
8/16/2011 4:14 PM
11-1328308Hardin
Will a bid item be added for approach slabs? 
REVISED ANSWER:
The Sepia Drawing on Sheet R42 was incorrectly inserted into the plan set.  It does not apply to this project.
8/16/2011 4:10 PM
11-1328308Hardin
Would the department consider paying the costs of the railroad flagman?
The contractor will pay flagging costs in accordance with the Special Notes for Protection of Railroad Interest.
8/16/2011 4:10 PM
11-1328308Hardin
Note 3 on Plan Sheet R2C indicates that the Temporary Concrete Barrier Wall shall become the property of KYTC upon completion of the project. However, the last line of paragraph “Center Pier #2” on Plan Sheet R30 states that the temporary barrier wall becomes the property of the contractor upon completion of the project. Which note is correct?
Plan Sheet R30 is in error.  Upon completion of the project the contractor shall deliver, unload, and stockpile Temporary Concrete Barrier Wall along KY 313 near MP 4.6 as directed by Engineer.
8/17/2011 8:10 AM
11-1036301Hardin
Material requirements for the Granular Embankment and Structure Backfill for the MSE Wall and Quantities.  Acceptance of Materials: is Resistivity and Direct Shear test required if quarry processed materials are used?  Also, is PH, Chlorides and Sulfates tests required if quarry material are used?
The reinforced MSE volume must meet Section 805.12 of the Standard Specifications.  This sections contains requirements for PH, Chlorides, and Sulfates.
8/17/2011 8:26 AM
11-1328308Hardin
What type of backfill will be required at the 3-sided culverts?  Will this backfill be paid for?
Construction of the two "3-Sided Culverts" will be in accordance with the general notes shown on sheets R101 and R102.  The approved alternatives are identified.  Per note 10, the backfill type is dependent upon the respective manufacturer and the alternative used.  With respect to payment for backfill, the aforementioned notes refer to KYTC Specification Section 603, which indicates backfill is an incidental item.
8/16/2011 4:10 PM
11-1036301Hardin
Is there a Crash Wall at the bottom of the MSE?
No, there is not a crash wall at the bottom of the MSE wall.  
8/17/2011 8:28 AM
11-1036301Hardin
Are the quantities for the Granular embankment and the Structure Granular Backfill for the MSE Wall only?
The quantity for the Granular embankment is for foundation replacement and external backfill at the MSE walls.  The Structure Granular Backfill is for the bridge not the MSE wall.
8/17/2011 8:27 AM
11-1036301Hardin
Concerning bid Item 21655ED, Remove Asbestos Pipe, is there any information about this bid item in the plans? Size of pipe, Depth of pipe, location on the project?
An addendum with a special note concerning the asbestos pipe removal will be posted to the website.
8/17/2011 8:18 AM
11-1036301Hardin
The notes (note 9) on the general summary correctly states that the wall is 14B (32) if asphalt shoulders are used and the bid item is for 50” wall.  Which is correct?
All walls will be 50”.  The note will be removed and an addendum posted to the website.
8/15/2011 3:21 PM
11-2950401Harlan
What is the penalty if the bridges are closed longer than the 4 and the 10 hours as discussed on page 10 of 58.
The contractor will pay liquidated damages for each hour or portion of an hour equal to the same amount referenced in Section 108.09.  Except instead of daily charge it will be considered hourly or portion of an hour.
8/15/2011 2:59 PM
11-1036301Hardin
Structure Drawing No. 26651 is titled “KY 1600 OVER DITCH”.  Shouldn’t this be “US 31W BYPASS OVER DITCH”?
Yes, Structure Drawing No. 26651 should be titled “US 31W BYPASS OVER DITCH”.
8/15/2011 3:21 PM
11-1036301Hardin
Is there any excavation/prep work required prior to constructing the barrier wall on the bypass?  Does the wall set on the existing asphalt? If so, are dowels required?
The barrier wall items will be moved to the pavement summary sheet to clarify the appropriate standard drawing since they are material dependant.  An addendum will be posted to the website.
8/15/2011 3:20 PM
11-1036301Hardin
Structure Drawing No. 26652 is titled “KY 1600 OVER DITCH”.  Shouldn’t this be “US 31W BYPASS OVER DITCH”?
Yes, Structure Drawing No. 26652 should be titled “US 31W BYPASS OVER DITCH”.
8/15/2011 3:21 PM
11-2950401Harlan
What is the scope of Jacking/Supporting on B00048N?
Jack and support bridge to allow for placement of shims as shown on page 18 of 58.
8/15/2011 2:56 PM
11-1036301Hardin
There is 150 lf of 12” bore and jack and 190 lf of 12” open cut steel encasement pipe described on plan sheet 51. This plan sheet describes the location but this line is not shown on the plans.  Can a plan and profile (pipe section) of this proposed line be provided? 
Yes, an addendum with that information will be posted to the website.
8/17/2011 8:28 AM
11-2303302Leslie
Will the wall have to have a rub finish?
No, but imperfections, such as honeycombing, will have to be corrected after removal of forms.
8/17/2011 4:28 PM
11-1036301Hardin
Please provide more information on "200AMP Meter Base with a By Pass Lever",  as noted at the bottom of page T-9.
Contact Nolin RECC at the number provided on plan sheet T9 for available manufacturers.
8/17/2011 8:44 AM
11-2303302Leslie
Is water fill station available on site?
Yes.
8/17/2011 4:28 PM
11-2303302Leslie
Can the contractor field bend the steel?
Yes
8/17/2011 4:28 PM
11-2303302Leslie
Will early cylinder breaks allowed?
Yes.
8/17/2011 4:28 PM
11-2303302Leslie
Will additives to allow for early strength be allowed?
No
8/17/2011 4:28 PM
11-2303302Leslie
Is electricity available on site?
No
8/17/2011 4:28 PM
11-2303302Leslie
Will a tremie have to be used?
No. Due to steel layout a tremie is not feasible.
8/17/2011 4:28 PM
11-2303302Leslie
Is water fill station available on site?
Yes.
8/18/2011 8:01 AM
11-2303302Leslie
Will a licensed surveyor be needed for the staking bid item to layout the building?
Contrary to the Standard Specifications, staking does not have to be performed by a licensed surveyor, but final layout shall be approved by the Engineer.
8/17/2011 4:28 PM
11-2303302Leslie
Can concrete trucks be washed out on site?
Yes, the contractor may excavate a hole across KY 118 from the maintenance facility for trucks to wash out. Fill the hole after completion of the project
8/17/2011 4:28 PM
11-1036301Hardin
Please provide the installation drawing specific to the project and the manufacturers contact information and representative for item line number 3080, Install Signal Sensor System.
The manufacturer information can be found at  http://www.sensysnetworks.com .  The exact locations of the sensors are shown in the bridge plans.
8/17/2011 8:47 AM
11-1331105Ohio
On Addendum #2,  Revised Sheet T2,  the 2nd to last item, "MAINTAIN AND CONTROL TRAFFIC (5%)".  Please explain 5%
The (5%) was inadvertently included in the bid item description, Maintain and Control Traffic.  Please disregard.
8/17/2011 2:36 PM
11-1036301Hardin
There is an existing 6' X 3' RCBC at Station 183+99.00 that the plans call to be removed for the installation of the new culvert.  However, there doesn't appear to be a Bid Item for the removal of this structure.  How will this be paid?
Removal of the culvert at Station 183+99.00 is incidental to the contract.  Please see Standard Specification 203.04.01.
8/17/2011 2:34 PM
11-1036301Hardin
Why are there two plan sheet T7's?
The “Signal Plan for KY 1600 @ US 31W Bypass Ramps” plan sheet should be labeled T8.
8/17/2011 2:40 PM
11-1036301Hardin
Please provide more information on Bid Item #3090 Install LED Sign.  Are there sign specifications, power requirements, installation instructions, etc.?
The sign is 36" x 36".  The manufacturer is Tapco and the Model No. is J-325956-112.  It is solar powered.  Installation instructions are per manufacturer's recommendation.
8/17/2011 2:33 PM
11-1037310Jefferson
Does a list of prequalified material suppliers exist for the lightweight modular sound wall?
There is no list of prequalified material suppliers for the lightweight modular sound wall.  A letter of certification has to be submitted by the contractor stating that the product meets KYTC specifications.
8/17/2011 2:42 PM
11-1036301Hardin
On plan sheet T7,  “Signal Plan for KY 1600 @ US 31W Bypass Ramps”, the "Service Note" on bottom of page, the last sentence states that the wire and extra disconnect is incidental to code 4931.  There is no pay item for the wood pole.  How will this be paid?
All work done under the service note will be incidental to bid code 4931.
8/17/2011 2:41 PM
11-1036301Hardin
Is there any additional information available for the subsurface data (soil/rock borings), such as the compressive strength of the rock?
All available subsurface data has either been provided in the contract documents or has been posted under project related information on the Construction Procurement website.
8/17/2011 3:18 PM
11-2303302Leslie
Will early cylinder breaks allowed?
Yes
8/18/2011 8:07 AM
11-2303302Leslie
Is electricity available on site?
No
8/18/2011 8:03 AM
11-2303302Leslie
Will a licensed surveyor be needed for the staking bid item to layout the building?
Contrary to the Standard Specifications, staking does not have to be performed by a licensed surveyor, but final layout shall be approved by the Engineer.
8/18/2011 8:04 AM
11-2972304Ballard
Will the state maintain the gravel on the road over the winter if the contractor does not have enough time to pave it?
Yes, the County will maintain the gravel approaches during the winter.
8/18/2011 8:18 AM
11-2967100Whitley
Will the contractor be allowed to come with their own jacking scheme other than the one that is proposed?
The contractor may submit a jacking scheme to the Engineer for consideration.
8/18/2011 8:09 AM
11-2303302Leslie
Will a tremie have to be used?
No. Due to steel layout a tremie is not feasible.
8/18/2011 8:06 AM
11-2967100Whitley
Is the jacking under a dead load and not a live load.  
Yes
8/18/2011 8:11 AM
11-2303302Leslie
Can concrete trucks be washed out on site?
Yes, the contractor may excavate a hole across KY 118 from the maintenance facility for trucks to wash out. Fill the hole after completion of the project
8/18/2011 8:07 AM
11-2972304Ballard
Is there a concern about the county road holding up in the fall with the heavy loads going in and out?
No
8/18/2011 8:20 AM
11-2967100Whitley
How many bearings are being replaced?
16
8/18/2011 8:10 AM
11-2972304Ballard
Will the 12/15/11 completion date would be affected by the acceptance of the environmental clearance?
The completion date will be offset by however long it takes to get the environmental clearance.
8/18/2011 8:17 AM
11-2972304Ballard
Can the 18” piles be changed to 14” concrete?  
No. The designer has stated that concrete piles will not be an acceptable replacement.
8/18/2011 8:19 AM
11-2973305Whitley
How many members are being replaced?
None of the main members are being replaced. The sway bracing is being modified, removed, and a kicker being put in to stiffen the corners and improve the clearance. Also, some vertical members are being straightened.
8/18/2011 8:08 AM
11-1036301Hardin
What is the intention of pay item 2040 – Sidewalk Ramp Type I – Normally they are paid for as sidewalk (SY) and not each.  Will these be paid for as EACH? 
The sidewalk ramps will be paid as noted.
8/18/2011 12:05 PM
11-1328308Hardin
Are piles acceptable for the arch foundations on this project?
Piles founded on bedrock, spread footings on soil with appropriate cyclopean stone rip-rap, or granular foundation replacement to bedrock are all acceptable foundations for the 3-sided precast structures at Sta. 124+55.18 and at Parkway Sta. 8420+59.80 as long as the requirements of the Structure Foundation Reports are followed.  The Structure Foundation Reports can be found at the following links:  http://kgs.uky.edu/kgsweb/kytc/Reports/SA-007-2011.pdf and http://kgs.uky.edu/kgsweb/kytc/Reports/SA-008-2011.pdf
8/18/2011 1:29 PM
11-2303302Leslie
Can the contractor field bend the steel?
Yes
8/18/2011 8:24 AM
11-2972304Ballard
Will the road needed to be bonded?
The contractor will be required to meet all regulations.  
8/18/2011 8:20 AM
11-2303302Leslie
Will the wall have to have a rub finish?
No, but imperfections, such as honeycombing, will have to be corrected after removal of forms.
8/18/2011 8:24 AM
11-1036301Hardin
Concerning item 0180/0670/0430 Cement Concrete Entrance 8”, the plan sheets only specifically indicate about 330 SY of concrete entrances vs the bid quantity of 1456 SY.  However, the paving summary indicates 609 sy entrances and 847 sy of Frontage Road 4.  Please clarify.
Beginning with plan sheet R17, the Concrete Entrance Construct notes are called out by note versus inclusion in a table.
8/18/2011 12:05 PM
11-2974306Hopkins
Is there a description/note for what material should be used, depth, etc. for Approach Pavement?
Materials
Class 2 Asphalt Surface 0.38 PG64-22.  This material shall be in accordance with the Standard Specifications.
Tack Coat.  This material shall be in accordance with the Standard Specifications
 
Construction
A.  Remove Existing Materials.  Remove the existing pavement material to provide for a minimum of 1¼” new  pavement surface from the bridge end extending approximately 100 feet into the approach pavement and across the width of the approach pavement.  The Engineer shall determine the actual length and width of the milling depending on site conditions at each bridge approach.  Mill the existing surface so that the new asphalt surface will tie into the new armored edge and matches the original cross section of the approach.  Mill a 3-foot edge key to tie the new surface into the existing surface approximately 100 feet from the bridge end.  The Engineer shall approve the Contractor’s plan for restoring the approach grade prior to the removal of the existing surface.  Dispose of all removed material entirely away from the job site or as directed by the Engineer.
           Backfill the area of pavement removed for placing the new armored edges with concrete of the same mix design as the overlay (minus the latex) to within 2” +/- of the top of the bridge end.  Allow this concrete to wet cure prior to placing the new asphalt surface on it.
B.  Produce and Place New Asphalt Surface. Apply an asphalt tack coat in accordance with Section 406.  Produce and place the new 1 ¼” asphalt surface in accordance with Section 403 and compact under Option B.  The new asphalt surface mixture required for this project shall be “Class 2 Asphalt Surface 0.38D PG 64-22”.  Place the new asphalt surface to the original roadway cross section or as directed by the Engineer.
C.   Treatment of Shoulders.  On roadways with paved shoulders, the shoulders shall receive identical treatment to the mainline pavement.  On roadways with earth or rock shoulders, the Contractor shall attempt to protect the shoulder from damage.  Any damage to earth or rock shoulders shall be repaired by the Contractor to the satisfaction of the Department at no additional cost.  These repairs may consist of re-grading, re-compacting, and/or placing millings to return the shoulder to its original cross section.
Measurement
     Will be in Square Yards
 
Payment
Payment at the contract unit price per square yard is full compensation for backfilling at the end of the structure, removing existing pavement markers, mobilization of milling equipment, removing specified existing pavement material, furnishing and installing the asphalt tack coat, producing and placing the new asphalt surface, shoulder treatment, and all incidental items necessary to complete the work within the specified pay limits as specified by this note.
The Department will consider payment as full compensation for all work required by these notes and detail drawings.
 
8/18/2011 2:38 PM